Calculate the CPI, SPI, CSI, and the ETC and EAC
A sales project at month 5 had an actual cost of $34,000, a planned cost of $42,000, and a value completed of $39,000. Find the cost and schedule variance and the CPI and SPI. A project to develop a county…